Energy Vault has closed $78 million in construction and bridge financing for its 150 MW/300 MWh SOSA battery storage project in Texas. The company expects commercial operations to begin in the third quarter of 2027.

Share This Post

Energy Vault Holdings, Inc. has closed $78 million in construction and bridge financing for the SOSA Energy Center, a 150 MW/300 MWh battery energy storage system in Madison County, Texas. The bridge financing will be repaid through an already committed $80 million preferred equity investment when the project is completed. Together with an additional draw on the existing OIC preferred facility, the financing is intended to support construction and commercial operation on a non-recourse basis.

SOSA was the first energy storage asset acquired and placed into development through Asset Vault, Energy Vault’s platform for owning and operating energy storage and artificial intelligence infrastructure assets. After completion, the project will operate on a merchant basis in the ERCOT North market, providing power and ancillary services. It will also have the flexibility to enter a contracted offtake agreement as market conditions change.

Construction began in the fourth quarter of 2025 after site control, environmental and interconnection milestones were put in place. Civil work has since been completed, and a substation has been installed. Energy Vault is performing the engineering, procurement and construction work. Major equipment is expected to arrive at the site in the coming months, with commercial operations planned for the third quarter of 2027.

According to Energy Vault, the project is expected to generate approximately $250 million to $300 million or more in long-term revenue and recurring EBITDA margins of about 65% to 75%. The SOSA Energy Center represents an investment of approximately $100 million in Madison County. The company estimates that it will generate $9.3 million in tax revenue for North Zulch Independent School District and Madison County over 10 years. Construction is also expected to create 65 local jobs.

SOSA financing · operation 3Q27

Energy Vault secures $78 million for Texas BESS

Energy Vault closed non-recourse construction and bridge financing to advance its Texas battery project toward commercial operation in 3Q27.

$78 millionConstruction and bridge financingSupports SOSA’s buildout on a non-recourse basis.
Financing
Preferred equityCommitted; repays bridge at completion$80 million
Construction + bridgeClosed for project buildout$78 million
System power150 MWBattery energy storage system with 300 MWh capacity.
Long-term revenue$250-300M+Expected with ~65% to 75% recurring EBITDA margins.
Local investment$100 millionApproximately; $9.3 million tax revenue over a 10-year period and 65 jobs.
Commercial operation3Q27Construction began in the fourth quarter of 2025; substation installed.

The $80 million preferred equity commitment is set to repay the bridge financing after project completion.

Construction fundedNon-recourse financing supports construction toward 3Q27 commercial operation, when SOSA is expected to serve ERCOT North through merchant power and ancillary services.
Energy Vault secures $78 million for Texas BESS · BatteryTech Network

Source: energyvault.com

Subscribe to Newsletter

Share This Post

Logo_Battery-Tech-Network_Thumbnail

Subscribe To Our
Weekly Newsletter​

Logo_Battery-Tech-Network_Thumbnail

Contact Form