ZE Energy Acquires Nearly 480 MWh Battery Site in Italy

ZE Energy — ZE Energy Acquires Nearly 480 MWh Battery Site in Italy
ZE Energy has acquired the fully authorized Magliano Alpi battery project in Piedmont, Italy. The 59 MW system will provide nearly 480 MWh of storage and connect to the 132 kV grid through an existing Terna substation.

Share This Post

ZE Energy, a French solar energy and storage specialist, announced on November 23, 2026, that it has acquired its third battery energy storage project in Italy. The Magliano Alpi project is located in the Piedmont region and was previously developed by Italian renewable energy developer ReFeel New Energy, which is backed by Gresham House Europe, formerly SUSI Partners.

The fully authorized, construction-ready project will have a power rating of 59 MW and a storage capacity of nearly 480 MWh, providing up to eight hours of operation. It will connect to the 132 kV high-voltage network through an existing Terna substation.

The battery system is intended to provide long-term flexibility to the northern Italian grid. It will be able to absorb electricity during periods of abundant generation and discharge it when demand is high or the electricity system is under pressure.

Italy’s electricity demand was projected to exceed 300 TWh in 2025, with net imports covering 15%. Photovoltaic generation exceeded 44 TWh during the year, representing a 25% year-over-year increase. Battery storage can absorb surplus solar generation during peak production periods and return electricity to the grid when renewable output is insufficient to meet demand.

ZE Energy is expanding its Italian battery portfolio through acquisitions as it works toward a target of 1.5 GW of installed capacity worldwide by 2030. Its first two Italian acquisitions were the 98.5 MW/832 MWh Sessa Aurunca battery project and the 200 MW/1.2 GWh Elena project, both identified in the source as being in the Puglia region.

Italy battery storage · 2025

ZE Energy Acquires Nearly 480 MWh Battery Site in Italy

The construction-ready project is ZE Energy’s third Italian acquisition, adding grid flexibility as photovoltaic output and import dependence rise.

480 MWhMagliano storage capacityNearly; fully authorized and construction-ready in Piedmont.
Storage capacity
Elena200 MW; Puglia; among first two1.2 GWh
Sessa Aurunca98.5 MW; Puglia; among first two832 MWh
Magliano AlpiPiedmont; third acquisitionnearly 480 MWh
Monfalcone12 MW; first project; end of 202412 MWh
Project power59 MWUp to eight hours; connected to the 132 kV network.
Power demand300 TWhProjected to exceed this in 2025; 15% covered by net imports.
Solar outputover 44 TWhProduced in 2025, a 25% year-on-year increase.
Capacity target1.5 GWWorldwide installed capacity by 2030.

Neutral markers indicate the source gives project capacities but no project-level year-on-year changes.

Why Storage MattersRising photovoltaic production and import dependence strengthen Italy’s need for storage that absorbs surplus electricity and returns it during system tension.
ZE Energy Acquires Nearly 480 MWh Battery Site in Italy · BatteryTech Network

The company has also developed the 12 MW/12 MWh Monfalcone project, which was commissioned at the end of 2024. Monfalcone was ZE Energy’s first battery storage project developed in Italy.

Source: Energy Storage