Evecon and Mirova Complete 250 MWh Estonian BESS

Evecon and Mirova logos
Evecon and Mirova have completed a 55 MW/250 MWh battery system at a 77.5 MW solar park near Lihula, Estonia. Final grid and market tests are underway for the hybrid project developed through their BREP joint venture.

Share This Post

Evecon and French investment manager Mirova announced on November 26, 2026, that a 55 MW/250 MWh battery energy storage system added to an operational 77.5 MW solar park near Lihula in western Estonia is technically complete. Final grid and market tests are being finalized.

The companies said the installation is the largest battery storage system by capacity in the Baltics and makes the site the region’s most powerful hybrid park. The solar farm was completed in October 2024. Evecon and Mirova subsequently invested €110 million ($120.7 million) to complete the hybridization through their joint venture, Baltic Renewable Energy Platform (BREP).

Construction of the battery system started in January this year. Tallinn-based construction company WiSo Engineering served as the main contractor, with responsibility for building the infrastructure and integrating the storage system. WiSo previously completed the Kirikmäe solar plant.

BREP has also entered into a ten-year flexibility and power purchase agreement with German energy company Pure Energy. The agreement covers output from the hybrid system and BREP’s 15.5 MW Imavere and 12.8 MW Lohu Mets solar plants. First announced in February, it was described as the first agreement of its kind in the Baltics.

At the time, BREP announced an €85 million long-term financing package from Swedbank. The funding supported the refinancing of its existing solar portfolio and construction of the Kirikmäe battery system.

Evecon CEO Karl-Joonatan Kvell called the completed hybrid project an important step toward greater Estonian energy security and an electricity system that relies more on domestic renewable energy. Estonia, Latvia and Lithuania have managed grid frequency independently since desynchronizing from the Russian grid and synchronizing with continental Europe in February 2025.

Other operational storage assets in Estonia include the 100 MW/200 MWh Hertz 2 system and the adjacent Hertz 1 system of the same capacity. Plans are also progressing for a 192 MW/420 MWh battery expected to become operational by November 2027.

Estonian BESS · current project status

Evecon and Mirova complete 250 MWh Estonian BESS

Adding the 55 MW/250 MWh system to 77.5 MW of solar creates what the owners call the Baltics’ most powerful hybrid park.

250 MWhBattery storage energy capacityOwners call it the Baltics’ largest-capacity battery storage system.
Energy capacity
Taaleri/KJK project192 MW; due November 2027420 MWh
Evecon/Mirova BESS55 MW; construction started January250 MWh
Hertz 2 BESS100 MW; switched on July200 MWh
Hertz 1 BESS100 MW; opened February200 MWh
Solar park77.5 MWOctober 2024; plus 15.5 MW Imavere, 12.8 MW Lohu Mets
Hybrid investment€110 million$120.7 million invested to complete hybridization
Financing€85 millionSwedbank long-term package for refinancing and the BESS
Offtake termten-year FPPAPure Energy agreement, first announced in February

No changes were reported; the 420 MWh build started in September, after Baltic frequency independence followed synchronization in February 2025.

Next hybrid forumOn Dec. 1, 2026 at 3 .p.m CET, five experts will discuss hybrid development and finance during four days of pv magazine Week Europe.
Evecon and Mirova complete 250 MWh Estonian BESS · BatteryTech Network

Source: Energy Storage

Subscribe to Newsletter

Share This Post

Logo_Battery-Tech-Network_Thumbnail

Subscribe To Our
Weekly Newsletter​

Logo_Battery-Tech-Network_Thumbnail

Contact Form