Terna Awards 16 GWh in Second Italian Storage Auction

Illustration: Terna Awards 16 GWh in Second Italian Storage Auction
Italy's second MACSE auction awarded 16 GWh of long-term battery storage contracts at an average €11,382/MWh-year. The pay-as-bid result was 12% below the first auction, with obligations starting in 2029.

Share This Post

Italian transmission system operator Terna announced on November 24 that its second Meccanismo di Approvvigionamento di Capacità di Stoccaggio Elettrico (MACSE) auction procured 16 GWh of long-term battery energy storage system capacity. Successful projects received 15-year revenue contracts through the pay-as-bid auction.

The auction was 60% larger than the first round in 2025. Its average clearing price was €11,382/MWh-year, 12% below the €12,959/MWh-year recorded in the previous auction. Terna awarded 2.8 GWh in Central-South at an average €10,716/MWh-year and 9.6 GWh in South and Calabria at €11,575/MWh-year.

Italy storage auction · 2026

Terna awards 16GWh as clearing price drops 12%

The second auction was 60% larger than 2025’s, yet cleared 12% lower, signalling intense price competition for contracted storage revenues.

16GWhBESS capacity awardedLong-term capacity in Southern Italy and its islands.
Awarded capacityShare
South and CalabriaAverage €11,575/MWh-year9.6GWh
Enel3 projects7,336MWh45%
SicilyAverage €11,467/MWh-year3 GWh
Central-SouthAverage €10,716/MWh-year2.8GWh
A2A4 projects; JV with BW ESS2,608MWh16%
FieldUK-headquartered developer-operator1,138MWh
SardiniaApproximately; €10,925/MWh/year0.5GWh
Clearing price€11,382/MWh-yearUS$12,449; 12% lower than €12,959/MWh-year in 2025.
Contract term15-year contractObligations start in 2029, versus 2028 for the 2025 auction.
Auction scale60% largerCompared with the first auction in 2025.
Competition2.7x capacityVersus 4x last year; 67GWh qualified and 43GWh bid.

The 16 winning projects include identified Enel and A2A shares of 45% and 16%; one academic estimated around 85% combined.

Certainty Gets CheaperFalling battery costs and deep supply supported lower bids, but thinner equity returns could follow and later clearing prices may fall further.
Terna awards 16GWh as clearing price drops 12% · BatteryTech Network

A further 3 GWh was awarded in Sicily at an average €11,467/MWh-year, while approximately 0.5 GWh was procured in Sardinia at €10,925/MWh-year. Terna said the volumes were calculated to ensure the cost of the new capacity remains below the expected benefit from reducing gas-fired generation costs.

Based on the project names in the published results, Enel secured three projects totaling 7,336 MWh, representing 45% of awarded capacity. A2A received contracts for four projects totaling 2,608 MWh, or 16%. BW ESS subsequently said the four projects are part of its joint venture with A2A. UK-headquartered battery storage developer and operator Field secured a 1,138 MWh project.

Project ownership shares could be higher because some successful project companies use generic names that do not identify their ultimate parent companies. The auction attracted 67 GWh of qualified capacity, with 43 GWh submitted for the available 16 GWh.

Obligations for the second auction will begin in 2029, compared with 2028 for projects selected in the 2025 auction. Although the contracts provide guaranteed revenue, operators must offer nearly all project capacity, leaving limited room for merchant market exposure. Industry observers said the lower prices could put pressure on equity returns and increase the importance of financing, engineering, procurement, construction and equipment costs.

Source: energy-storage.news

Subscribe to Newsletter

Share This Post

Logo_Battery-Tech-Network_Thumbnail

Subscribe To Our
Weekly Newsletter​

Logo_Battery-Tech-Network_Thumbnail

Contact Form